3 Answers

Hi,

I can understand your frustration, especially when renovation delays start affecting your moving plans.

However, I think the priority now should be establishing a realistic completion schedule rather than simply asking the contractor to speed things up.

I would suggest arranging a proper meeting with the contractor or project manager to establish:

1. What work has been completed and what remains outstanding.
2. The actual reasons for the delays, including any material or manpower shortages.
3. A revised schedule showing when each remaining stage will be completed.
4. Whether additional manpower or adjustments to the work sequence can realistically shorten the delay.

Most importantly, get the revised timeline and commitments documented in writing.

You should also review your renovation agreement to see whether there are provisions relating to completion deadlines, delays or compensation.

I would be careful about making further payments ahead of agreed milestones or engaging another contractor without first understanding your contractual obligations.

May I know how many weeks your renovation has been delayed, and how much work is still outstanding?

Also, are you dealing directly with a contractor or through an interior design company with an appointed project manager?

If you recently purchased the property through an agent, have you approached your agent for any recommendations or assistance? While renovation project management is generally outside an estate agent's responsibilities, an experienced agent may be able to point you towards useful resources.

Ultimately, what you need now is accountability and a workable recovery plan, not another series of explanations for missed deadlines.

Geryl Lim
 9278 7772  Read More
1
Silas Tan 陈敬良
Hi, ask for a written recovery programme rather than another general assurance. List every unfinished task, the material or approval it depends on, who is responsible and the proposed completion date. Have the project manager identify the actual bottleneck.

Agree regular progress updates with dated photos and compare them with the programme. Avoid rushing work that needs drying, curing, testing or inspection; finishing quickly is not useful if it creates defects.

Check the contract’s delay and payment provisions before agreeing extra charges, changing scope or engaging someone else. If deadlines keep slipping without a credible plan, escalate to the company’s management and consider CASE or legal advice. How late is the project, and which tasks are holding up the rest?

Silas Tan | Huttons | TRIBE
Free property guides and calculators: https://tribesg.com Read More
0
Gan Eng Joo ONASSIS
**Freeze any further progress payments immediately and shift from verbal chasing to a written, milestone-enforced recovery schedule.** Shifting excuses usually point to subcontractor bottlenecks, cash-flow strain, or delayed material orders—and financial leverage is your strongest tool to restore urgency.

---

### 1. Immediate Steps to Speed Up Works

* **Hold Upcoming Payments:** Do not release another cent until completed physical milestones pass your on-site inspection.
* **Demand a Written Catch-Up Schedule:** Require a dated task-by-task timeline via WhatsApp or email within 48 hours covering remaining trades (wet works, electrical, carpentry delivery, painting).
* **Verify Material & Permit Status:** Ask for proof of submitted HDB/MCST permits and supplier delivery orders for long-lead items (tiles, sintered stone, carpentry carcasses) to expose real bottlenecks.
* **Visit the Site Weekly:** Unannounced or scheduled physical checks with timestamped photos prevent your unit from being deprioritized for other clients.

---

### 2. Contractual & Legal Leverage in Singapore

* **Enforce Liquidated Damages (LAD):** Check your contract for daily late-completion penalties (standard in CaseTrust-accredited contracts) and notify the contractor in writing that you reserve your right to deduct LAD from the final balance.
* **Issue a Formal Notice to Complete:** If stalls continue, send a dated written notice giving a reasonable final deadline (e.g., 14 days) to resume active work, warning that continued delay constitutes a breach allowing termination and engagement of a replacement contractor at their cost.
* **Escalate If Unresolved:** Lodge a complaint with **CASE** (for mediation), **HDB** (if using an HDB-registered contractor), or file a claim at the **Small Claims Tribunals** (up to S$20,000, or S$30,000 with mutual consent).

---

Gan Eng Joo Onassis 颜荣裕, REALTOR®

MSc BIT (Middlesex, UK); BBA (UniSA)

CEA Reg No: R021244C | Mobile: (+65) 8889 9918 

Email: onassis@sgagent.com

SGAgent.com | SGRealtor.com | SGCommercial.com | SGCBD.com

SGShowflat.com | SGNewLaunch.com

Integrated Services: SGCash.com | SGRepair.com | SGLegal.com

Social (Facebook & TikTok): @sgcommercial Read More
0

Still looking for answers?

Get answers from PropertyGuru experts in 24 hours

Previously Asked Questions