My condo renovation is currently halfway done almost 50 to 60 % and already there are many things that look different from what i thought I agreed to. Nothing is completely unusable, but some carpentry details, colours and measurements are not what i expected. i thought verbal discussions during the design process were enough for small details but now I’m starting to regret not documenting everything.
0 •
13 views
Want this question answered?
Get faster responses from our experts by upvoting.
Be the first to upvote this question.

4 Answers

Hi,

Since your renovation is already 50–60% completed, I would suggest addressing the discrepancies now rather than waiting until everything is installed.

The first thing is to compare the actual work against your signed quotation, approved drawings, material selections and any written communications.

For items that differ from what was formally agreed, arrange a meeting with your interior designer or contractor to clarify the discrepancies and agree on the necessary rectifications.

For details that were only discussed verbally, it may be more difficult to establish exactly what was agreed upon. Nevertheless, you can still try to negotiate a reasonable solution.

I would also suggest documenting all outstanding issues and getting written confirmation of any changes before the remaining work proceeds.

As property agents, our professional expertise is primarily in property transactions rather than renovation design, carpentry or construction disputes.

Your interior designer or renovation contractor would therefore be in a better position to address the technical aspects, while CASE may be able to assist if the matter develops into a consumer dispute.

I hope you manage to resolve the issues before the renovation progresses further.

Geryl Lim
 9278 7772  Read More
1
Silas Tan 陈敬良
Hi, address the differences now, before later work makes them harder to correct. Create a list showing each item, what you expected, what was installed, and the supporting drawing, sample, quotation or message. Take dated photos and measurements.

Meet the project manager to distinguish an actual departure from the agreed specification from a detail that was never finalised. Ask for written agreement on rectification, cost responsibility and any timing impact. For disputed items, seek an agreed hold on the affected work while the issue is clarified.

For the remaining renovation, approve drawings, material codes, colours and dimensions in writing before fabrication. Do not assume verbal promises will resolve a disagreement later. If you cannot agree on what the contract requires, consider CASE or legal advice with the records you have.

Silas Tan | Huttons | TRIBE
Free property guides and calculators: https://tribesg.com Read More
0
Gan Eng Joo ONASSIS
**Pause upcoming milestone payments immediately and shift all remaining renovation approvals from verbal to written sign-offs.** At 50%–60% completion, you still hold strong financial leverage to rectify discrepancies before final installation.

---

### 1. Immediate Action Plan (Do This Today)

* **Conduct a Joint Site Walkthrough:** Walk through every room with your Interior Designer (ID) or contractor and bring all original 2D/3D renders, laminate samples, and WhatsApp chat logs.
* **Separate "Deviations" from "Preferences":**
* *Contractor Error (Free Rectification):* Anything that contradicts your signed quotation, 2D elevation drawings, or written WhatsApp confirmations (e.g., wrong laminate code, wrong cabinet height) must be rectified at the contractor's expense.
* *Verbal Misunderstandings (Negotiate Shared Cost):* For undocumented verbal details, negotiate a fair middle ground—ask them to absorb labour if you cover minor material costs, or swap easily changeable items (handles, shelving heights, paint coats).

* **Issue a Written Rectification List:** Send a numbered list with photos via WhatsApp/email summarizing agreed fixes and completion dates before releasing the next progressive payment.

---

### 2. Lock Down the Remaining 40%–50%

* **Require Signed 2D Elevation Drawings:** Before remaining carpentry leaves the factory, insist on dimensioned 2D drawings showing internal shelving, hinge sides, socket cutouts, and exact laminate codes.
* **Confirm Paint & Hardware Physically On-Site:** Test paint swatches on the actual wall under your unit's lighting before full coats are applied, and verify handles/tracks in person.
* **Hold Back Final Retention (5%–10%):** Never release the final payment tranche until every defect on your handover checklist is rectified.

---

Gan Eng Joo Onassis 颜荣裕, REALTOR®

MSc BIT (Middlesex, UK); BBA (UniSA)

CEA Reg No: R021244C | Mobile: (+65) 8889 9918 

Email: onassis@sgagent.com

SGAgent.com | SGRealtor.com | SGCommercial.com | SGCBD.com

SGShowflat.com | SGNewLaunch.com

Integrated Services: SGCash.com | SGRepair.com | SGLegal.com

Social (Facebook & TikTok): @sgcommercial Read More
0
Hi,

1) It is not uncommon to see different effect based on only verbal description during a renovation.
2) Not only must be properly paper documented, illustration photos also must be accompany with it.
3) Sad to say the quality of renovation in town is still not up to standard.
4) On the other hand, most of the design you saw on magazines, newspaper, tik-tok, faccebook, etc, are taken with different lightings. The density of lights do provide a different atmosphere on different materials.
5) Thus, the same materials present in different lightings could gives you a different opinion.
6) It is too late to regrets now since already more than half done. Regular checks and provide a variation orders (pay more) to the contractor could help to reduce disappointment at the end of the day.

All The Best!!!

I hope the above answers your main concerns. If you have more questions, please feel free to contact me at 9011*0636 or email ling.ck7@gmail.com for more information.
I'll be glad to assist.

Best regards
Ling CK
9011 * 0636
ling.ck7@gmail.com
https://www.linkedin.com/in/ckling/
https://agents.huttonsgroup.com/R056727F/ Read More
1

Still looking for answers?

Get answers from PropertyGuru experts in 24 hours

Previously Asked Questions