18 HDB neighbourhood renewal projects delayed by over six months

Cheryl Chiew3 Nov 2021

construction-singapore

Out of 32 projects, 18 HDB neighbourhood renewal projects are either fully or partially delayed by a period of over six months.

With the COVID-19 pandemic posing severe challenges to the construction industry, 18 out of 32 Neighbourhood Renewal Programme (NRP) projects that are under construction have been delayed – in full or in part – by over six months, revealed the Ministry of National Development (MND).

“All 18 projects have resumed construction works progressively since October 2020, and are estimated to be completed within the next two to three years,” it said in Parliament on Monday (1 November).

It was responding to MP Ng Ling Ling, who asked about the number of NRP projects that have been delayed by over six months and the estimated time to clear the backlog.

On whether support for raw material prices would be extended to contractors working on such projects, MND explained that support for raw material prices is applicable for Housing and Development Board (HDB) Build-To-Order (BTO) projects that “have a contractual provision for protection of price fluctuation of certain materials”.

And since works at NRP projects are generally not as complex, the Town Councils – which implement such projects – “do not include such a contractual provision for the contractors in their tenders”.

Thus, the support measure for raw material prices does not apply to contractors of NRP projects.

“Nonetheless, NRP contractors affected by COVID-19 can tap on other relief measures provided under the COVID-19 (Temporary Measures) Act (COTMA), and Town Councils will assess if the relief measures (e.g. prolongation and manpower costs) are applicable to their NRP contracts,” said MND.

The ministry pointed that the Building and Construction Authority (BCA) had also announced on 3 November 2020 the universal Extension of Time of 122 days for private and public sector contracts affected by the COVID-19 pandemic.

With this, Town Councils can “also review further EOT periods with the contractors accordingly”.

Looking for a property in Singapore? Visit PropertyGuru’s ListingsProject Reviews and Guides.

Cheryl Chiew, Digital Content Specialist at PropertyGuru, edited this story. To contact her about this story, email: cheryl@propertyguru.com.sg

POST COMMENT

You may also like these articles

HDB contractors to receive more help for protection of material prices

HDB revealed that it would extend the duration of steel price protection by nine months, up from its earlier extension of four months, to help cushion the impact of price hikes.Construction firms work

Continue Reading16 Sep 2021

Lawsuits brewing for contractors as COVID-19 legal relief ends

On 30 September 2021, the relief period under the Covid-19 (Temporary Measures) Act will end, which may lead to many SMEs facing financial distress and affecting the sector at large.Contractors in Sin

Continue Reading27 Sep 2021

Average wait times for BTO projects remains at four to five years, says Desmond Lee

The total waiting time for BTO projects is still under six years, with BTO projects launched this year and last year having wait times ranging between three to 5.5 years.Including delays brought abo

Continue Reading6 Oct 2021

Two-thirds of BTO projects completed during the pandemic delayed no more than six months

17 BTO projects completed during the pandemic did not see a delay past six months, with 16,000 flats being delivered since January 2020.Flat buyers at 17 Build-to-Order (BTO) projects that were comple

Continue Reading13 Oct 2021