89 ongoing BTO projects have received BCA's approval to resume works: Desmond Lee

Victor Kang24 Aug 2020

Lee also reassured homeowners that HDB will “continue to do their best to minimise these delays for all other BTO projects, while working with contractors to ensure COVID-safe compliance”. Photo: HDB

The Building and Construction Authority (BCA) has approved 89 ongoing Build-to-Order (BTO) projects to resume works, including Senja Valley HDB BTO project in Bukit Panjang, said Minister for National Development Desmond Lee. 

He had visited the project site on Friday, where he observed the COVID-19 safety measures put in place by the contractor – Sim Lian Construction.

These include segregation of workers and work zones, which means fewer workers are being assigned for jobs within the same zones.

Recommended article: Are BTO Flats Making Us Delusional About Property Prices?

This also means that some works take longer to complete than during pre-COVID times, said Lee on his Facebook post.

He noted that the project’s contractors had put extra effort to regularly consult with relevant agencies, “and ensure detailed manpower planning, site preparation, as well as train their workers to maintain safe distancing”.

With this, the minister thanked the contractor and their sub-contractors for their commitment to prevent the resurgence of COVID-19 and for doing their best to deliver the projects on time.

“Abiding by these safety measures may lead to inevitable delays, but they are needed for everyone’s health and safety,” he said.

Lee also reassured homeowners that HDB will “continue to do their best to minimise these delays for all other BTO projects, while working with contractors to ensure COVID-safe compliance”.

Read also: 5 BTO Projects That Have Recently Crossed their 5-Year HDB MOP in 2020

 

Looking for a property in Singapore? Visit PropertyGuru’s ListingsProject Reviews and Guides.

Victor Kang, Digital Content Specialist at PropertyGuru, edited this story. To contact him about this or other stories, email victorkang@propertyguru.com.sg

POST COMMENT

You may also like these articles

Construction projects may be delayed by months

Faced with limited manpower, material shortages and the circuit breaker measures, construction projects are set to be pushed back.  Contractors expect construction projects to be delayed by months e

Continue Reading27 Apr 2020

Government has placed a range of measures for homeowners affected by construction delays

HDB and URA have been exercising flexibility on a case-by-case basis for households who are in genuine difficulty and need temporary accommodation, according to Lawrence Wong. The government has put

Continue Reading27 May 2020

New condo residents frustrated over delayed rectification works due to COVID-19

Developers say that it's difficult to provide rectification works as the government has halted all construction works in April. With the COVID-19 pandemic disrupting renovation and construction works

Continue Reading17 Aug 2020