Downtown Line 2 to open in Q1 2016

Muneerah 30 Sep 2014

During a site visit to the upcoming Bukit Panjang MRT station on the Downtown Line, Minister for Transport Lui Tuck Yew (pictured, left) said the government is confident of opening the Downtown Line 2 (DTL2) earlier by the first quarter of 2016.

Tunnelling of DTL2 has been completed in June this year, two months ahead of the revised schedule, the Ministry of Transport said in a statement.

According to media reports, DTL2 experienced some issues when one of its main contractors went into insolvency and halted work on the Sixth Avenue, King Albert Park and Tan Kah Kee stations.

However, the Land Transport Authority (LTA) and its contractors managed to recover some of the time lost by adding manpower, re-organising the workflow and innovative work processes.

“LTA and all the contractors will continue to work hard to recover more of the time and bring forward the opening to even earlier than first quarter of 2016 … many of them have been working round the clock, seven days a week. But all these acceleration must be done without compromising safety standards,” Lui said in media reports.

DTL2 is 16.6 km long and will comprise 12 stops connecting Bukit Panjang to Bugis.

Image source: Ministry of Transport’s Facebook page

 

Muneerah Bee, Senior Journalist at PropertyGuru, wrote this story. To contact her about this or other stories email muneerah@propertyguru.com.sg

POST COMMENT

You may also like these articles

Lake Life to launch 14 months after site was acquired

Lake Life is set to be the first Executive Condominium (EC) to beat the 15 months government regulation to launch e-applications this Saturday.Developers who acquired EC land parcels after 11 Janu

Continue Reading30 Sep 2014

Green buildings make business sense

Incorporating environmental sustainability into a building’s design and operation makes business sense, according to Minister for the Environment and Water Resources Dr Vivian Balakrishnan, as utili

Continue Reading30 Sep 2014